About

Projects

Talk to us

Have questions? Reach out to us directly.

Geyer Sanitary Relief and Windsor Springs P-521 Storage

View all

As part of a long-term effort to reduce basement backups and sewer overflows, MSD Project Clear is designing a project to replace undersized sewers in the Cities of Kirkwood and Sunset Hills, and improve the Windsor Springs pump station.

This project is estimated to begin construction in Fall 2021.

View Sept 1, 2020 Virtual Town Hall Project Presentation

Why is this project being designed?

A number of residents have experienced building back-ups, partly due to overcharged sewers that cannot handle the increased amount of flow experienced during rainfall.

In addition, during heavy rain events, the pump station at Windsor Springs also becomes overcharged. The pump station forces water through our system where gravity cannot.

What is the goal of this project?

MSD Project Clear is investing approximately $5.5 million to design this project to increase the size and depth of the existing sewer and improve the Windsor Springs pump station.  This will alleviate existing problems resulting from undersized sewers.

Project Facts

  • Construction is estimated to begin Fall 2021.
  • MSD Project Clear will replace approximately 6,600 feet of wastewater sewer.
  • The pipe size will increase to between 10 to 12-inches in diameter allowing a larger amount of wastewater to flow through the system.
  • The Windsor Springs pump station will be improved and the generator will be replaced.
  • Removal of inflow sources from private properties.

What can residents expect?

Though construction for this project is not estimated to begin until Fall 2021, it is important to be prepared for what to expect. By January 2021, residents whose property will need to be accessed to construct the project will be contacted in order to obtain necessary easements.

Type of Construction:

With any type of construction, residents can expect to see and hear heavy equipment during the sewer excavation process. The majority of this project will be constructed by a method known as “tunneling” underneath Geyer Rd. This means that at multiple locations a tunnel boring machine will be set up to dig through the soil and rock and push the new pipe into place. Tunneling is being used in this area to ensure that the surface of Geyer Road is disturbed as little as possible.

Traffic Impact:

As a part of this project, MSD Project Clear does expect traffic impacts to roads in this area. Construction near and on Big Bend Boulevard and Geyer Road will require temporary lane closures. More specific information including timing and locations of these closures will become available once the project has a Contractor and they can determine a set schedule.

MSD Project Clear does not expect any access issues to homes or businesses. The Contractor will provide notice to affected residents before construction takes place.

Restoration:

After all new sewer pipes are installed, the Contractor will restore the construction site according to all District and local requirements. This could include sodding any disturbed areas, replacing disturbed pavement, reinstalling fences, etc. More detail on this will become available after a Contractor is selected for the project ahead of construction in the Fall of 2021.

What is the timeline?

This is the current tentative project schedule. This is subject to change based on a variety of factors including weather.

  • Project design completion: August 2020
  • Easement acquisition completion: January 2021
  • Estimated construction start: Fall 2021
  • Estimated project duration: Two years, Fall 2023

Image Gallery

Talk to us

Have questions? Reach out to us directly.