Valley Drive Sanitary Relief Phase III (13444)

View all

As part of a long-term effort to reduce basement backups and sewer overflows, MSD Project Clear is constructing a project to replace approximately 5,500 feet of undersized wastewater sewers in the cities of Clarkson Valley and Ballwin.

About the Project

What is the goal of this project?

MSD Project Clear is investing approximately $4 million to improve wastewater sewers in the cities of Clarkson Valley and Ballwin. The goal is to reduce basement backups and sewer overflows, which occur when the sewers become overloaded during intense rainfall. This project will reduce such occurrences by increasing the size and capacity of the existing sewer.

Project Facts

  • Construction is estimated to begin in January 2024. (Currently delayed until further notice due to contractor staffing)
  • MSD Project Clear will replace approximately 5,500 feet of wastewater pipe.
  • The pipe size will increase to between 8 and 15-inches in diameter, allowing a larger amount of wastewater to flow through the system.

How will it be built?

Most of this project will be constructed by digging through the surface, a process known as “open-cut.” The contractor will dig a trench several feet into the ground, remove the old sewer pipe, and replace it with a newer, larger pipe.

What can residents expect?

This project will be constructed by digging through the surface of the ground in a process known as “open-cut” construction. The pictures above depict what a neighborhood will look like before, during and after a typical open-cut project.

With any type of construction, residents can expect to see and hear heavy equipment during the sewer excavation process.

Traffic and Access: As much of the construction will take place in the street, Wetherburn Road between Downall Green Drive and Capitol Landing Drive may be closed to through traffic for up to five days during construction of this project. A detour plan will be in place during the closure. Residents should expect temporary lane closures on Golfview Drive, Del Ebro Drive, Kettington Road and Richborough Road. MSD Project Clear will maintain at least one lane of traffic at all times to allow property owners to enter and exit. Traffic control will be provided as needed.

Similarly, construction may lead to temporarily limited access to some properties along the construction route. Restrictions will be limited to active construction hours, and the contractor will notify property owners in advance of any access restrictions.

Restoration: After all new sewer pipes are installed, the contractor will restore the construction site according to all MSD and local requirements. This could include sodding any disturbed areas, replacing disturbed pavement, reinstalling fences, etc.

At least one MSD Inspector will be on-site part of the day for every day the contractor is working.

What is the timeline?

This is the current tentative project schedule. This is subject to change based on a variety of factors, including weather.

  • Estimated construction start: January 2024 (Currently delayed until further notice due to contractor staffing)
  • Estimated construction duration: 24 months