About

Projects

Talk to us

Have questions? Reach out to us directly.

Woodson Sanitary Relief (12300)

View all

As part of a long-term effort to reduce basement backups and sewer overflows, MSD Project Clear is constructing a project to install approximately 2,800 feet of wastewater sewers in the City of Overland.

About the Project

What is the goal of this project?

MSD Project Clear is investing approximately $2 million to improve wastewater sewers in the City of Overland. The goal is to reduce basement backups and sewer overflows, which occur when the sewers become overloaded during intense rainfall. This project will reduce such occurrences by increasing the size and capacity of the existing sewer. It will also allow MSD to eliminate 2 sanitary sewer overflow points.

Project Facts

  • Construction is estimated to begin in Spring 2024.
  • MSD Project Clear will construct approximately 2,800 feet of wastewater pipe.
  • The pipe size will increase to between 8 and 21-inches in diameter, allowing a larger amount of wastewater to flow through the system.

What can residents expect?

This project will be constructed by digging through the surface of the ground in a process known as “open-cut” construction. The pictures above depict what a neighborhood will look like before, during and after a typical open-cut project.

With any type of construction, residents can expect to see and hear heavy equipment during the sewer excavation process.

TRAFFIC: MSD Project Clear does expect traffic disruptions as a part of this project. There will likely be temporary lane closures, road closures, and/or detours. Impacted roadways in which construction will take place include Wabaday Avenue, Seneca Lane, Goodale Avenue, South Milton Avenue, and Sycamore Way.

RESTORATION: After all new sewer pipes are installed, the contractor will restore the construction site according to all MSD and local requirements. This could include sodding any disturbed areas, replacing disturbed pavement, reinstalling fences, etc.

At least one MSD Inspector will be on-site part of the day for every day the contractor is working.

What is the timeline?

This is the current tentative project schedule. This is subject to change based on a variety of factors, including weather.

  • Estimated construction start: Spring 2024
  • Estimated construction duration: 21 months

Image Gallery

Talk to us

Have questions? Reach out to us directly.